Cameroon-Chad Power Link’s First Phase Now Estimated at CFA145 Billion on Cameroon’s Side

Issu de TV+ AFRIQUE

An October 2026 African Development Bank assessment mission revised the cost of the first phase of Cameroon's side of the Cameroon-Chad Power Interconnection

Cameroon-Chad Power Link’s First Phase Now Estimated at CFA145 Billion on Cameroon’s Side

Ce qu'il faut retenir

  • The first phase of Cameroon's section of the power interconnection with Chad is estimated to cost CFA145.2 billion.
  • The project aims to enable electricity exports of 100 megawatts to Chad by 2030.
  • The cross-border component faced a CFA287 billion financing shortfall in late 2025.
  • Formal approval of the project restructuring must occur before construction contracts can be signed.

An October 2026 African Development Bank assessment mission revised the cost of the first phase of Cameroon's side of the Cameroon-Chad Power Interconnection Project (PIRECT) to €221.3 million (CFA145.2 billion). The restructured plan, known as Option 2-bis, includes 426 km of high-voltage transmission lines and substation works aimed at exporting 100 MW of power to Chad by 2030. The new estimate follows a CFA287 billion project financing gap identified in late 2025. Bids for transmission lines and substations are due in mid-November 2026, though final formal approvals for the restructured plan remain pending.

Determines the scope and timeline for initial electricity trade between Cameroon and Chad.

Regarder le récap

Les chiffres clés

€221.3M
Estimated cost for first phase of Cameroon's section
CFA145.2B
Estimated project cost for Cameroon's section first phase
426 km
High-voltage transmission lines planned in October presentation
100 MW
Target electricity exports to Chad by 2030
CFA287B
Total financing gap identified in November 2025

Le fil des événements

  1. 2025-08-07 Joint Technical Committee adopts Option 2-bis restructuring plan
  2. 2025-11 Minister Gaston Eloundou Essomba reveals CFA287B financing gap
  3. 2026-08-12 AfDB publishes tenders specifying 419.6 km transmission lines
  4. 2026-10-12 AfDB conducts assessment mission to review project restructuring
  5. 2026-10-19 Mission meets in N'Djamena to prepare restructuring report

Transformez ces actus en vues

Ravenclip repère les actus Politique, crée la vidéo et la publie avant que le buzz ne retombe.

Créer ma chaîne

Source: Google News

Questions fréquentes

Que s'est-il passé avec Cameroon-Chad Power Interconnection Project ?
The first phase of Cameroon's section of the power interconnection with Chad is estimated to cost CFA145.2 billion.
Où puis-je lire le rapport d'origine ?
Retrouvez le rapport complet sur Google News.